Main services
Circular No. 05/2009/TT-BXD dated April 15, 2009 of the Ministry of Construction guiding the adjustment of work construction cost estimates
09/06/2011
Share |

THE MINISTRY OF CONSTRUCTION
------

No. 05/2009/TT-BXD

SOCIALIST REPUBLIC OF VIET NAM
Independence - Freedom – Happiness
--------

Hanoi, April 15, 2009

 

CIRCULAR

GUIDING THE ADJUSTMENT OF WORK CONSTRUCTION COST ESTIMATES

 

Pursuant to the Government's Decree No. 17/2008/ND-CP of February 4, 2008, defining the functions, tasks, powers and organizational structure of the Ministry of Construction;

Pursuant to the Government's Decree No. 12/2009/ND-CP of February 12, 2009, on management of investment projects on the construction of works

Pursuant to the Government's Decree No. 99/2007/ND-CP of June 13, 2007, on management of work construction investment expenses (below referred to as Decree No. 99/200/VND-CP); and the Government's Decree No. 03/2008/ND-CP of January 7, 2008, amending and supplementing a number of articles of Decree No. 99/2007/ND-CP of June 13, 2007, on management of work construction investment expenses;

Pursuant to the Government's Decree No. 110/2008/ND-CP of October 10, 2008, prescribing the region-based minimum wage level applicable to laborers working in Vietnamese companies, enterprises, cooperatives, cooperative groups, farms, households, individuals and other-employers (below referred to as Decree No. 110/2008/ND-CP);

Pursuant to the Construction Ministry's Circular No. 03/2008/TT-BXD of January 25,2008, guiding the adjustment of work construction cost estimates (below referred to as Circular No. 03/ 2008/TT-BXD);

Pursuant to the Labor, War Invalids and Social Affairs Ministry's Circular No. 23/2008/TT-BLDTBXH of October 20, 2008, promulgating the Guidance on implementation of the region-based minimum wage level applicable to state companies and one-member limited liability companies in which the State owns 100% of charter capital;

The Ministry of Construction guides the adjustment of work construction cost estimates as follows:

I. GENERAL PROVISIONS

1. This Circular guides the adjustment of cost estimates from January 1, 2009, using the minimum wage level applicable based on regions (where works are constructed) under Decree No. 110/2008/ ND-CP, for the remaining volumes of works or bidding packages (below referred to as work construction cost estimates) under uncompleted state-funded investment projects on the construction of works for which investment deciders have not yet decided to change the management of work construction investment expenditures under Decree No. 99/2007/ND-CP.

It is encouraged to apply this Circular's provisions on the adjustment of work construction cost estimates to work construction investment projects funded with capital of other sources.

2. To adjust work construction cost estimates formulated using construction, installation and construction survey unit prices set by provinces or centrally run cities on the basis of wage scales in wage table A. 1.8 enclosed with the Government's Decree No. 205/2004/ND-CP of December 14, 2004, prescribing the system of wage scales and wage tables and allowances applicable to state companies (below referred to as Decree No. 205/ 2004/ND-CP), and the minimum wage level of VND 450,000/month, as prescribed in the Appendix to this Circular.

3. For works for which separate unit prices or machine shift costs have been formulated using the minimum wage level promulgated by a competent person, their construction cost estimates will be adjusted using the new region-based minimum wage level on the principles and methods guided in this Circular.

4. Adjustment of contractual prices or amounts paid for work volumes performed from January 1, 2009, under signed contracts and contractual terms: If the involved parties have agreed in a contract not to adjust prices during the implementation process, the investor and construction contractor may negotiate and supplement the contract in order to ensure laborers' interests under regulations.

II. SPECIFIC PROVISIONS

1. Work construction cost estimates formulated using construction unit prices set by provinces or centrally run cities on the basis of the minimum wage level of VND 450,000/month under the Government's Decree No. 94/2006/ND-CP of September 7, 2006, adjusting the common minimum wage level, and wage scales in wage table A. 1.8 enclosed with Decree No. 205/2004/ND-CP. will be adjusted as follows:

1.1. Adjustment of construction cost estimates

1.1.1. Adjustment of labor expense

Labor expense in construction cost estimates formulated using local construction unit prices shall be multiplied by an adjustment coefficient (KDCNC) in compliance with the region-based minimum wage level.

The adjustment coefficient (KDCNC) is equal to the new region-based minimum wage level divided by the minimum wage level already included in the unit price.

1.1.2. Adjustment of construction machine expense

Construction machine expense in construction cost estimates formulated using local construction unit prices shall be multiplied by an adjustment coefficient (KDCMTC) in compliance with the region-based minimum wage level and fuel and energy prices applicable in January 2009.

The adjustment coefficient (KDCMTC) of construction machine expense is determined by calculating the weighted average expense, depending on each group of machines.

According to the above principle, the coefficient for adjusting construction machine expense (KDCMTC) in construction cost estimates made by provinces and centrally run cities is guided in the Appendix to this Circular. For provinces or cities with a peculiar construction structure, their People's Committees shall decide on the adjustment coefficient of construction machine expense.

For works constructed in lines running through several provinces or centrally run cities for which separate machine-shift price tables have been formulated, investors shall calculate and report adjustment coefficients to investment deciders for decision. For works under investment projects on the construction of works in which investment is decided by the Prime Minister, ministers, heads of ministerial-level agencies, heads of government-attached agencies, presidents of provincial-level People's Committees, chairmen of economic groups or chairmen of boards of directors of state corporations shall decide on adjustment coefficients.

1.1.3. Expenses calculated in proportion (%) to construction cost estimates

Expenses calculated in proportion (%) to construction cost estimates, including other direct expense, common expense, pre-calculated taxable income, value-added tax, expense for the construction of makeshift houses at construction sites for accommodation and construction administration, must comply with regulations.

1.2. Adjustment of construction survey cost estimates

Labor expense in construction survey cost estimates (KDCNCKS) shall be adjusted using the coefficients specified in the Appendix to this Circular.

In case work construction cost estimates formulated under Point 1 of this Section have been adjusted under the guidance of Circular No. 03/ 2008/TT-BXD: When adjusting the cost estimate using the new region-based minimum wage level, labor expense and construction machine expense in construction cost estimates and labor expense in construction survey cost estimates shall be further multiplied by the corresponding adjustment coefficient which equals the adjustment coefficient using the new region-based minimum wage level specified in the Appendix to this Circular divided by the used adjustment coefficient under Circular No. 03/2008/TT-BXD.

3. Some other expenses in work construction cost estimates

Expenses for management of investment projects on the construction of works, work construction designing, construction supervision and installation of equipment of works specified at Point 1 of Section I above are calculated in a percentage (%) under regulations.

III. ORGANIZATION OF IMPLEMENTATION

1. Investors shall adjust, and approve results of adjustment of, work construction cost estimates for remaining volumes performed from January 1. 2009. of construction works under investment projects on the construction of works as specified at Point 1, Section I of this Circular. If approved work construction cost estimates result in an excess of the total investment, investors shall report such to investment deciders for consideration and decision. Ministers, heads of ministerial-level agencies, heads of government-attached agencies, presidents of provincial-level People's Committees, chairmen of economic groups or chairmen of boards of directors of state corporations shall decide on the adjustment of cost estimates for construction works under investment projects on the construction of works in which investment is decided by the Prime Minister.

2. For construction works for which separate unit prices have been formulated (work construction unit prices), investors shall, based on regimes and policies applicable to works as permitted by the State and principles of adjusting work construction cost estimates guided in this Circular, determine levels of adjustment of labor expense, construction machine expense and other expenses (if any) in work construction cost estimates.

3. Investors shall decide on the adjustment of construction cost estimates for works under investment projects on the construction of works under Decree No. 99/2007/ND-CP.

This Circular takes effect 45 days from the date of its signing.

 

 

FOR THE MINISTER OF CONSTRUCTION
VICE MINISTER




Cao Lai Quang

 

APPENDIX

(To the Construction Ministry's Circular No. 05/2009/TT-BXD of April 15, 2009)

To adjust cost estimates of remaining volumes performed from January 1, 2009, of construction works under uncompleted investment projects as specified at Point 1, Section I of this Circular.

1. Adjustment of construction cost estimates

1.1. Adjustment of labor expense or construction machine expense

Labor expense or construction machine expense in construction cost estimates shall be multiplied by the adjustment coefficient (KDCNC) or (KI)CMTC) specified in Table 1 in this Appendix.

1.2. Expenses calculated in proportion (%) to construction cost estimates.

Other direct expense, common expense, pre-calculated taxable income, value-added tax and expense for the construction of makeshift houses at construction sites for accommodation and construction administration shall be calculated in percentage (%) under regulations.

2. Adjustment of construction survey cost estimates

Labor expense in construction survey cost estimates shall be multiplied by the adjustment coefficient (KDCNCKS) specified in Table 2 in this Appendix.

3. Adjustment of cost estimates for testing construction materials and structure

Labor expense in cost estimates for testing construction materials and structure determined using norms and unit prices for testing construction materials and structure enclosed with the Construction Minister's Decision No. 32/2001/QD-BXD of December 20, 2001, shall be multiplied by the adjustment coefficient (KDCNCTN) specified in Table 3 in this Appendix.

4. Other expenses calculated in proportion (%) to work construction cost estimates shall be determined
according to the State's current regulations.

Table 1. Adjustment coefficients for construction cost estimates

Region-based minimum

Wage
level

Adjustment
coefficient

Region I

Region II

Region III

Region IV

 

VND 800,000/month

VND 740,000/month

VND 690,000/month

VND 650,000/month

For labor expense (KDCNC)

1.78

1.64

1.53

1.44

For construction machine expense (KDCMTC)

1.2

1.18

1.16

1.14

Table 2. Adjustment coefficients for construction survey cost estimates

Region-based minimum

Wage
level

Adjustment
coefficient

Region I

Region II

Region III

Region IV

 

VND 800,000/month

VND 740,000/month

VND 690,000/month

VND 650,000/month

For labor expense (KDCNCKS)

1.78

1.64

1.53

1.44

Table 3. Adjustment coefficients for cost estimates for testing construction materials and structure

Region-based minimum

Wage
level

Adjustment
coefficient

Region I

Region II

Region III

Region IV

 

VND 800,000/month

VND 740,000/month

VND 690,000/month

VND 650,000/month

For labor expense (KDCNCTN)

4.2

3.88

3.62

3.41

 

LIST OF GEOGRAPHICAL AREAS IN WHICH REGION-BASED MINIMUM WAGE LEVEL IS APPLICABLE

Regions

Geographical areas

 

 

I

- Urban districts of Hanoi;

- Urban districts of Ho Chi Minh City.

II

- Gia Lam, Dong Anh, Soc Son, Thanh Tri, Tu Liem, Thuong Tin, Hoai Due, Dan Phuong, Thach That and Quoc Oai districts, and Son Tay town, of Hanoi;

- Rural districts of Ho Chi Minh City;

- Urban districts and Thuy Nguyen and An Duong districts of Hai Phong city;

- Urban and rural districts of Da Nang city;

- Ninh Kieu and Binh Thuy districts of Can Tho city;

- Ha Long city of Quang Ninh city;

- Bien Hoa city, Long Khanh town, and Nhon Trach, Long Thanh, Vinh Cuu and Trang Bom districts, of Dong Nai province;

- Thu Dau Mot town and Thuan An, Di An, Ben Cat and Tan Uyen districts, of Binh Duong province;

- Vung Tau city and Tan Thanh district of Ba Ria-Vung Tau province.

 

III

- Provincial cities (except those of Region II);

- Remaining rural districts of Hanoi;

- Bac Ninh city, Tu Son town and Que Vo, Tien Du and Yen Phong districts, of Bac Ninh province;

- Bac Giang city and Viet Yen and Yen Dung districts, of Bac Giang province;

- Hung Yen city and My Hao, Van Lam, Van Giang and Yen My districts, of Hung Yen province;

- Hai Duong city and Cam Giang, Nam Sach, Chi Linh, Kim Thanh and Kinh Mon districts, of Hai Duong province;

- Vinh Yen city and Phuc Yen town of Vinh Phuc province;

- Remaining rural districts of Hai Phong city;

- Mong Cai city and Uong Bi and Cam Pha towns of Quang Ninh province;

- Da Lat city and Bao Loc town of Lam Dong province;

- Nha Trang city and Cam Ranh town of Khanh Hoa province;

- Trang Bang district of Tay Ninh province;

- Remaining rural districts of Binh Duong province;

- Remaining rural districts of Dong Nai province;

- Tan An town, and Due Hoa, Ben Luc and Can Duoc districts, of Long An province;

- Remaining urban and rural districts of Can Tho city;

- Ba Ria town, and Chau Due, Long Dien, Dat Do and Xuyen Moc districts, of Ba Ria-Vung Tau province.

 

IV

- Remaining geographical areas.

 

         

 

 

updating...
Older Documents
Online Support
Liên hệ bằng Yahoo! Messenger
If you need advice, please contact via Yahoo! Messenger to get online help.

Lawyer in Hanoi
Contact via Skype
You can use Skype to get online help
Skype Me™!
Search legal documents
Latest Documents
Advertising
Site Information

 
 
 

© Copyright: 2011 DRAGON LAW FIRM  - All rights reserved


Hotline: 1900. 599. 979

Mật ong nguyên chấtChuyên cung cấp sỉ và lẻ mật ong nguyên chất 100% tại TPHCM từ thiên nhiênDịch vụ điện hoa Hoa Tươi 360o với dịch vụ điện hoa chuyên nghiệp, giá hợp lý giúp bạn gởi đến người thân những bó hoa tươi đẹp nhấtShop hoa phong lan Hoa tươi 360o là shop hoa phong lan TPHCM chuyên cung cấp các loại hoa lan hồ điệp và địa lanHoa giỏ Hoa giỏ để bàn tạo cho không gian làm việc trở nên cực kỳ ấn tượng, được sử dụng trong các dịp như đám cưới, tặng sếp, sinh nhật....Hoa bó Hoa tươi 360o giúp bạn gởi đến bạn bè, người thân hoa bó chúc mừng sinh nhật, tốt nghiệp, hoa tặng sếp nam giá hợp lý, giao hoa miễn phí TP. HCMhoa chúc mừng Hoa tươi 360o chuyên điện hoa chúc mừng khai trương: kệ hoa khai trương, giỏ hoa khai trương... với giá hợp lý, giao hoa miễn phí trong TPHCMHoa chia buồn Hoa tươi 360o chuyên điện hoa chia buồn ở TPHCM với giá cả hợp lý, giao hoa miễn phí ở TPHCMHoa chúc mừng sự kiện Hoa chúc mừng sinh nhật, hoa chúc mừng sự kiện tặng bạn bè hoặc người thân những dịp trọng đại, giao hoa miễn phí nội thành TPHCMShop hoa cưới Hoa cưới đẹp giúp đám cưới của bạn thêm ý nghĩa. Gọi 1900 545 587 để được shop hoa cưới - Hoa tươi 360o tư vấn, giao hoa cưới miễn phí ở Bình Thạnh và tại TPHCMhoa tươi Shop Hoa tươi 360o với dịch vụ hoa tươi giúp bạn gởi đến người thân những bó hoa tươi đẹp - giá hợp lý, giao hoa miễn phí tại TPHCMĐặt quần áo đá banh Đặt quần áo bóng đá - Đặt quần áo đá banh ở TPHCM với chất lượng tốt, giá ưu đãi. Gọi 0903 009 041 để Đặt quần áo bóng đá - Đặt quần áo đá banhGiày Futsal PAN Thái LONI chuyên cung cấp các loại giày Futsal PAN Thái Lan giá rẻ trên toàn quốc. Gọi 0903 009 041 gặp MS. Nhi để đặt giày Futsal Pan Thái  giá rẻgiày đá banh cỏ tự nhiên LONI Sport chuyên cung cấp các loại giày đá banh cỏ tự nhiên giá rẻ với nhiêu mẫu mã đẹpGiày đá banh cỏ nhân tạo LONI SPORT kinh doanh sỉ và lẻ giày bóng đá, giày đá banh cỏ nhân tạo, giày futsal Pan Thái Lan với giá cạnh tranh kèm quà tặng hấp dẫngiày đá banh LONI SPORT kinh doanh sỉ và lẻ giày đá banh, giày bóng đá cỏ nhân tạo Fake1, giày futsal Pan Thái Lan với giá cạnh tranh kèm quà tặng hấp dẫnáo bóng đá - áo đá banh LONI Sport chuyên thiết kế và sản xuất quần áo đá banh, áo bóng đá ở TPHCM. Quý khách đặt áo đá banh vui lòng liên hệ: 0983 031 509 - 0903 009 041Shop quần áo đá banh - Shop bán đồ thể thao Shop bán đồ thể thao Loni Sport chuyên bán quần áo đá banh, phụ kiện thể thao như: giày đá banh, túi xách, vớ ...Gọi 0983 031 509 - 0903 009 041DỰ ÁN CĂN HỘ NEWTON RESIDENCE DỰ ÁN CĂN HỘ NEWTON RESIDENCE sẽ chính thức mở bán vào 30/2/2016. LH mua CĂN HỘ NEWTON RESIDENCE 0903414547-0933333188Thay mặt kính Ipad Thay mặt kính Ipad giá rẻ nhất TP. HCM, lấy liền có bảo hànhThay mặt kính Samsung Thay mặt kính Samsung giá rẻ nhất TP. HCM, lấy liền có bảo hànhthay mat kinh Iphone Thay mặt kính Iphone giá rẻ nhất TP. HCM, lấy liền có bảo hànhThay mặt kính Iphone 6S Thay mặt kính Iphone 6S giá rẻ nhất TP. HCM, đặc biệt chờ lấy liền. Nhận thay mắt kính Iphone 6S cho các cửa hàng Cọc khoan nhồi Nền Móng Đất Phương Nam chuyên thi công cọc khoan nhồi mini với phương pháp và thiết bị hiện đại, đội ngũ nhân viên chuyên nghiệp. Gọi ngay 0919 49 8080Phụ kiện nhà bếp Inox 304 Phụ kiện nhà bếp bằng Inox 304 do Hòa Bình Glass sản xuất và phân phối giúp cho các bà nội trợ nhanh chóng giải quyết vấn đề dầu mỡ vì dễ lau chùi, tiện lợi và nhanh chóngGương soi phòng tắm Gương soi phòng tắm do Hòa Bình Glass sản xuất từ nguyên liệu kính Guardian của Mỹ với nhiều mẫu mã phong phúPhụ kiện phòng tắm Hobig chuyên sản xuất và phân phối phụ kiện phòng tắm, liên hệ để có bảng giá sỉ phụ kiện phòng tắm phù hợp cho mọi nhàPhụ kiện nhà bếp Hòa Bình Glass chuyển sản xuất và phân phối phụ kiện nhà bếp. Liên hệ để có bảng giá phụ kiện nhà bếp cho đại lýthay mặt kính Iphone 6s Plus thay mặt kính Iphone 6s Plus giá rẻ nhất TP. HCM, đặc biệt chờ lấy liền và có bảo hành đầy đủ

Thám tử Văn phòng luật sư |   Luật sư bào chữaVietnam lawfirm |  Quảng cáo trực tuyến |  Thiết bị camera |  đại lý vé máy bay |  Thám tử hà nội | dịch vụ thám tử | Thám tử tại hà nội | thám tử sài gòn | thuê thám tử tại sài gòn | Thám tử tại sài gòn | Thám tử hải phòng | Thám tử | Thám tử tư |
quảng cáo facebook